Follow-up audit model of government investment project based on synergy theory
LI Dong, WANG Yao-wu, SONG Hui, ZHAO Li-dan
Systems Engineering - Theory & Practice ›› 2013, Vol. 33 ›› Issue (2) : 405-412.
Follow-up audit model of government investment project based on synergy theory
The disharmony of government investment projects was introduced, which essence is in long-term state out of control and lack of supervision. Based on synergy and follow-up audit theory, the follow-up audit objective system on the real thinking was established. The integrated performance and subsystems synergy were analyzed. The result of analysis show that optimization of subsystems was not necessarily able to improve the integrated performance level of the project. Whether the subsystems were optimized to strengthen the integrated synergy was the key to improve the integrated performance level of the project. The higher the synergy degree, the higher integrated performance level. Synergy audit aimed to raise integrated performance level was put forward, and was different with audit cooperation. The evaluation index system of synergy audit was erected. Synergy degree was introduced as quantitative evaluation audit index. The theory analysis and empirical research show that synergy audit is practically able to improve the integrated performance level and the introduction of synergy degree makes it operable.
synergy / follow-up audit / government investment project {{custom_keyword}} /
[1] 刘家义. 刘家义在全国审计工作会议上的讲话(节选)[J]. 中国内部审计, 2009(1): 2-9.Liu J Y. Liu Jiayi's speech at the national audit conference (excerpt)[J]. Internal Audit of China, 2009(1): 2-9.
[2] 贺桂珍, 吕永龙, 刘达朱, 等.挣值管理在环境审计中的应用[J]. 审计研究, 2007(2): 3-8.He G Z, Lü Y L, Liu D Z, et al. Earned value management and its application in government environmental audit[J]. Auditing Research, 2007(2): 3-8.
[3] 陈全民. 中国政府绩效审计模式研究[D]. 北京: 中国农业大学, 2005.Chen Q M. Study on the model of performance audit in government in China[D]. Beijing: China University of Agriculture, 2005.
[4] 潘开灵, 白烈湖. 管理协同理论及其应用[M]. 北京: 经济管理出版社, 2006.Pan K L, Bai L H. Management Synergy Theory and Its Applications[M]. Beijing: Economic Management Publishing House, 2006.
[5] H.哈肯.高等协同学[M]. 郭治安,译. 北京: 科学出版社, 1989.Haken H. Higer Synergy[M]. Beijing: Science Press, 1989.
[6] 时现, 朱尧平, 薛蓓儿. 建设项目跟踪审计路径选择[J]. 审计与经济研究, 2006, 21(3): 8-11.Shi X, Zhu Y P, Xue B E. Alternatives for follow-up audit of construction projects[J]. Audit and Economy Research, 2006, 21(3): 8-11.
[7] 曹慧明. 建设项目跟踪审计[M]. 北京: 中国财政经济出版社, 2010.Cao H M. Follow-up Audit of Construction Project[M]. Beijing: China Financial and Economic Publishing House, 2010.
[8] 杨建平.政府投资项目协同治理机制及其支撑平台研究[D]. 北京: 中国矿业大学, 2010.Yang J P. Research on cooperative governance mechanism and its support platform in government investment project[D]. Beijing: China University of Mining and Technology, 2010.
[9] 陈光, 成虎. 建设项目全寿命期目标体系研究[J]. 土木工程学报, 2004, 37(10): 87-91.Chen G, Cheng H. Total lifecycle objective system of construction project[J]. China Civil Engineering Journal, 2004, 37(10): 87-91.
[10] 吴绍艳. 基于复杂系统理论的工程项目管理协同机制与方法研究[D]. 天津: 天津大学, 2006.Wu S Y. Study on the synergetic mechanism and methods of construction project management based on complex system theory[D]. Tianjin: Tianjin University, 2006.
[11] 席酉民, 尚玉钒. 和谐管理理论[M]. 北京: 中国人民大学出版社, 2002.Xi Y M, Shang Y F. Harmony Management Theory[M]. Beijing: China Renmin University Press, 2002.
[12] 曾珍香. 可持续发展协调性分析[J]. 系统工程理论与实践, 2001, 21(3): 18-21.Zeng Z X. The analysis of coordination and sustainable development[J]. Systems Engineering — Theory & Practice, 2001, 21(3): 18-21.
[13] 毛绮, 张雪楠.浅议审计协同实践框架的构建[J]. 审计研究, 2007(6): 31-34.Mao Q, Zhang X N. The research on the establishment of audit coordination system's practical framework[J]. Auditing Research, 2007(6): 31-34.
[14] 毛明来. 和谐理念下的投资项目经济评价研究[D]. 天津: 天津大学, 2007.Mao M L. Research on economic evaluation of investment projects based on the concept of harmony[D]. Tianjin: Tianjin University, 2007.
[15] Anbari F T. Earned value project management method and extensions[J]. Project Management Journal, 2003, 33(4): 12-23.
[16] 李冬, 王要武, 赵丽丹. 基于挣值审计理论开展我国建设项目跟踪审计[J]. 东北农业大学学报:社科版, 2009(6): 44-48.Li D, Wang Y W, Zhao L D. Follow-up auditing of Chinese infrastructure project based on earned value audit theory[J]. Journal of Northeast Agricultural University: Social Science Edition, 2009(6): 44-48.
/
〈 |
|
〉 |