钢箱梁生产的提前/拖期调度问题研究

桂玲, 谢勇, 王红卫

系统工程理论与实践 ›› 2017, Vol. 37 ›› Issue (5) : 1274-1281.

PDF(779 KB)
PDF(779 KB)
系统工程理论与实践 ›› 2017, Vol. 37 ›› Issue (5) : 1274-1281. DOI: 10.12011/1000-6788(2017)05-1274-08
论文

钢箱梁生产的提前/拖期调度问题研究

    桂玲, 谢勇, 王红卫
作者信息 +

Early/tardy scheduling problem for the steel box girders production and construction

    GUI Ling, XIE Yong, WANG Hongwei
Author information +
文章历史 +

摘要

本文以港珠澳大桥钢箱梁生产供应过程为研究对象,建立了钢箱梁生产的提前/拖期优化调度模型,并且针对模型的特点提出了一种基于启发式规则的改进遗传算法,在最优开工时间的基础上加入了拖期工件的剔除规则,有效地解决了工序不确定情况下的提前/拖期优化调度问题,并与无剔除规则的遗传算法进行比较,发现改进的方法在最优成本和收敛速度方面都有较大的改善.

Abstract

The steel box girders' production and installation play a great role in construction of the Hongkong-Zhuhai-Macao Bridge. We develop an early/tardy scheduling model for the production of steel box girders. And then an improved genetic algorithm based on heuristic rules has been proposed. A tardiness job filtering rule has been integrated to the genetic algorithm on the basis of the optimal time algorithm, which effectively solves the early/tardy problem without ex ante sequencing the jobs. The numerical study from Hongkong-Zhuhai-Macao examples proves that our proposed algorithm can improve the cost and to speed up the convergence.

关键词

钢箱梁 / 提前/拖期调度 / 遗传算法 / 最优开工时间

Key words

steel box girder / early/tardy scheduling / genetic algorithm / the optimal timing algorithm

引用本文

导出引用
桂玲 , 谢勇 , 王红卫. 钢箱梁生产的提前/拖期调度问题研究. 系统工程理论与实践, 2017, 37(5): 1274-1281 https://doi.org/10.12011/1000-6788(2017)05-1274-08
GUI Ling , XIE Yong , WANG Hongwei. Early/tardy scheduling problem for the steel box girders production and construction. Systems Engineering - Theory & Practice, 2017, 37(5): 1274-1281 https://doi.org/10.12011/1000-6788(2017)05-1274-08
中图分类号: TP202+.7   

参考文献

[1] Baker K R, Scudder G D. Sequencing with earliness and tardiness penalties: A review[J]. Operations Research, 1990, 38(1): 22-36.
[2] Sidney J B. Optimal single-machine scheduling with earliness and tardiness penalties[J]. Operations Research, 1977, 25(1): 62-69.
[3] Lakshminarayan S, Lakshmanan R, Papineau R L, et al. Technical note-optimal single-machine scheduling with earliness and tardiness penalties[J]. Operations Research, 1978, 26(6): 1079-1082.
[4] Yano C A, Kim Y D. Algorithms for a class of single-machine weighted tardiness and earliness problems[J]. European Journal of Operational Research, 1991, 52(2): 167-178.
[5] Lee C Y, Choi J Y. A genetic algorithm for job sequencing problems with distinct due dates and general early-tardy penalty weights[J]. Computers & Operations Research, 1995, 22(8): 857-869.
[6] Nadjafi B A, Shadrokh S. A branch and bound algorithm for the weighted earliness-tardiness project scheduling problem with generalized precedence relations[J]. Scientia Iranica, 2009, 16(1): 55-64.
[7] Nadjafi B A, Shadrokh S. An algorithm for the weighted earliness-tardiness unconstrained project scheduling problem[J]. Journal of Applied Sciences, 2008, 8(9): 1651-1659.
[8] Bauman J, Józefowska J. Minimizing the earliness-tardiness costs on a single machine[J]. Computers & Operations Research, 2006, 33(11): 3219-3230.
[9] James R J W, Buchanan J T. A neighborhood scheme with a compressed solution space for the early/tardy scheduling problem[J]. European Journal of Operational Research, 1997, 102(3): 513-527.
[10] Vanhoucke M, Demeulemeester E, Herroelen W. An exact procedure for the resource-constrained weighted earliness-tardiness project scheduling problem[J]. Annals of Operations Research, 2001, 102(1-4): 179-196.
[11] 于海斌, 薛劲松, 王浩波,等. 基于遗传算法的单机提前/拖期调度方法研究[J].控制理论与应用, 2000, 17(2): 209-214.Yu H B, Xue J S, Wang H B, et al. GA-based approach to single machine scheduling with general early-tardy penalty weights[J]. Control Theory & Application, 2000, 17(2): 209-214.

基金

国家自然科学基金重大项目(71390524);国家自然科学基金面上项目(61174147)