基于元网络的项目组织学习能力对任务完成影响评价仿真方法

李永奎, 庞达, 李东宇, 卢昱杰

系统工程理论与实践 ›› 2016, Vol. 36 ›› Issue (5) : 1252-1260.

PDF(2238 KB)
PDF(2238 KB)
系统工程理论与实践 ›› 2016, Vol. 36 ›› Issue (5) : 1252-1260. DOI: 10.12011/1000-6788(2016)05-1252-09
论文

基于元网络的项目组织学习能力对任务完成影响评价仿真方法

    李永奎1, 庞达1, 李东宇1, 卢昱杰2
作者信息 +

Meta-network simulation to evaluate the effect of project organization learning ability on task completion

    LI Yongkui1, PANG Da1, LI Dongyu1, LU Yujie2
Author information +
文章历史 +

摘要

组织能力是影响项目任务完成的决定性因素,而学习能力是组织能力形成的关键基础.基于元网络理论和动态仿真方法,将组织(人)、知识和任务视为多智能体复杂交互系统,提出知识扩散度和任务完成水平两项关键指标,研究项目组织学习能力对任务完成水平影响的内在机理.以通用品牌别克汽车4S店建设项目群管理为例,验证评价指标的合理性,并进一步通过仿真实验,识别项目组织的关键知识、关键组织以及关键学习阶段,进行组织学习能力提升和任务分配的优化,为项目组织设计、任务分配及组织学习的研究探索了一种有效的方法.

Abstract

Organization ability is the critical factor for project task completion, and learning ability is crucial basis for organizational ability formation. Based on meta-network theory and dynamic simulation method, this paper regards organization (people), knowledge and task as complex interactive system of multi-agent and puts forward 2 measurement indexes (knowledge diffusion and task completion), researching the internal mechanism of learning ability of project organization to influence task completion. Finally, taking General Motors (GM) Buick 4S Shop Construction Project Group Organization as a case, this paper further identifies the key knowledge, key agent and key learning phase of project organization through simulation after reasonable confirmation of measurement indexes and optimizes organization learning ability and task assignment. Furthermore, this paper provides effective methodology for research of project organization design, optimization of task assignment and organization learning.

关键词

元网络 / 项目组织学习 / 知识扩散 / 任务完成水平 / 仿真

Key words

meta-network / project organization learning / knowledge diffusion / task completion / simulation

引用本文

导出引用
李永奎 , 庞达 , 李东宇 , 卢昱杰. 基于元网络的项目组织学习能力对任务完成影响评价仿真方法. 系统工程理论与实践, 2016, 36(5): 1252-1260 https://doi.org/10.12011/1000-6788(2016)05-1252-09
LI Yongkui , PANG Da , LI Dongyu , LU Yujie. Meta-network simulation to evaluate the effect of project organization learning ability on task completion. Systems Engineering - Theory & Practice, 2016, 36(5): 1252-1260 https://doi.org/10.12011/1000-6788(2016)05-1252-09
中图分类号: C936   

参考文献

[1] Moon I. Destabilization of adversarial organization with strategic interventions[D]. Carnegie Mellon University, 2008, CMU-ISR-08-124.
[2] Gordon A F. Ghostly matters:Haunting and the sociological imagination[M]. University of Minnesota Press, 2008.
[3] Chinowsky P S, Taylor J E. Project networks:Leadership, learning, and development[J]. CIB Priority Theme-Revaluing Construction:A W065 ‘Organisation and Management of Construction’ Perspective, 2007:54.
[4] 李永奎, 乐云, 何清华, 等.大型复杂项目组织网络模式及实证分析[J].同济大学学报(自然科学版), 2011, 39(6):930-934.Li Y K, Le Y, He Q H, et al. Large and complex projects organization social network model and empirical study[J]. Journal of Tongji University (Nature Science), 2011, 39(6):930-934.
[5] Chinowsky P, Taylor J E, Di Marco M. Project network interdependency alignment:New approach to assessing project effectiveness[J]. Journal of Management in Engineering, 2010, 27(3):170-178.
[6] 李永奎, 乐云, 何清华, 等. 基于SNA的复杂项目组织权力量化及实证[J]. 系统工程理论与实践, 2012, 32(2):312-318. Li Y K, Le Y, He Q H, et al. Complex projects organization power quantification and empirical study based on SNA[J]. Systems Engineering-Theory & Practice, 2012, 32(2):312-318.
[7] Maurer M. Process optimization by DSM-based modelling of inputs and outputs[C]//DS 68-1:Proceedings of the 18th International Conference on Engineering Design (ICED 11), Impacting Society through Engineering Design, Vol. 1:Design Processes, Lyngby/Copenhagen, Denmark, 15.-19.08. 2011.
[8] Charrel P J, Galarreta D, Charrel P J, et al. Project management and risk management in complex projects[M]. Springer, 2007.
[9] Lyneis J M, Cooper K G, Els S A. Strategic management of complex projects:A case study using system dynamics[J]. System Dynamics Review, 2001, 17(3):237-260.
[10] Chen Y M, Wei C W. Multiagent approach to solve project team work allocation problems[J]. International Journal of Production Research, 2009, 47(13):3453-3470.
[11] Zafra-Cabeza A, Ridao M A, Camacho E F. Using a risk-based approach to project scheduling:A case illustration from semiconductor manufacturing[J]. European Journal of Operational Research, 2008, 190(3):708-723.
[12] Teo H H, Wang X, Wei K K, et al. Organizational learning capacity and attitude toward complex technological innovations:An empirical study[J]. Journal of the American Society for Information Science and Technology, 2006, 57(2):264-279.
[13] 高俊山, 毛建军, 谷冬元. 组织学习能力综合评价模型研究[J]. 管理学报, 2008, 5(2):212-217.Gao J S, Mao J J, Gu D Y. Research on the comprehensive evaluation model of organizational learning capability[J]. Chinese Journal of Management, 2008, 5(2):212-217.
[14] Tohidi H, Jabbari M M. Presenting structural equation model for measuring organizational learning capability[J]. Procedia Technology, 2012, 1:586-590.
[15] 何清华, 罗岚, 陆云波, 等.基于TO视角的项目复杂性测度研究[J].管理工程学报, 2013(1):127-134. He Q H, Luo L, Lu Y B, et al. Investigating project measurement complexity from TO perspectives[J]. Journal of Industrial Engineering/Engineering Management, 2013(1):127-134.
[16] 杨婧, 陈英武, 沈永平.基于相互作用网络的大型工程项目组织结构风险分析[J].系统工程理论与实践, 2011, 31(10):1966-1973. Yang J, Chen Y W, Shen Y P. Interdepedent network based risk analysis of organizational structures for large-scale engineering project[J]. Systems Engineering-Theory & Practice, 2011, 31(10):1966-1973.
[17] Frantz T L, Carley K M, Wallace W A. Computational organization theory[M]//Encyclopedia of Operations Research and Management Science, Springer US, 2013:246-252.
[18] Hanneman R A, Riddle M. Introduction to social network methods[R]. Department of Sociology University of California Riverside, 2005.
[19] Nagurney A, Wakolbinger T, Zhao L. The evolution and emergence of integrated social and financial networks with electronic transactions:A dynamic supernetwork theory for the modeling, analysis, and computation of financial flows and relationship levels[J]. Computational Economics, 2006, 27(2-3):353-393.
[20] Carley K M, Filonuk D T, Joseph K, et al. Construct user guide[R]. CASOS Technical Report CMU-ISR-112, Carnegie Mellon University:Pittsburgh, USA, 2012.
[21] Li Y, Lu Y, Li D, et al. Metanetwork analysis for project task assignment[J]. Journal of Construction Engineering and Management, 2015, 141(12):04015044.
[22] Lorscheid I, Heine B O, Meyer M. Opening the ‘black box’ of simulations:Increased transparency and effective communication through the systematic design of experiments[J]. Computational and Mathematical Organization Theory, 2012, 18(1):22-62.
[23] Carley K M, Lee J S, Krackhardt D. Destabilizing networks1[J]. Connections, 2002, 24(3):79-92.
[24] Hirshman B R, Morgan G P, St Charles J R, et al. Construct demo input deck[R]. School of Computer Science, Carnegie Mellon University, 2010.
[25] McPherson M, Smith-Lovin L, Cook J M. Birds of a feather:Homophily in social networks[J]. Annual Review of Sociology, 2001:415-444.
[26] Hollingshead A B. Perceptions of expertise and transactive memory in work relationships[J]. Group Processes & Intergroup Relations, 2000, 3(3):257-267.
[27] Carley K M. Computational organizational science and organizational engineering[J]. Simulation Modelling Practice and Theory, 2002, 10(5):253-269.
[28] 王红丽, 陆云波.可计算组织模型的验证难点与验证方法综述[J].系统工程理论与实践, 2014, 34(2):382-391.Wang H L, Lu Y B. Overview of computational organization model validation concerns and its methodology[J]. Systems Engineering-Theory & Practice, 2014, 34(2):382-391.